Call Centre Go-Live Checklist: UAT, Cutover and Day One

A call centre go-live checklist: user acceptance tests for every call path, a phased cutover with rollback, day-one hypercare and the first two weeks.

Contact centre team testing calls before go-live with an engineer

The weeks of planning for a new contact centre come down to one morning: the day real customers call. A go-live goes well when every path a caller can take has been tested, the team knows what to do when something breaks, and there is a way back if it goes badly. This call centre go-live checklist covers the last stretch: user acceptance testing (UAT), the cutover plan, day-one support and the first two weeks. If you are still at the planning stage, start with how to set up a call centre in India.

Two weeks before go-live: freeze and test

Stop changing the design two weeks out. Every change after that needs a retest, and late changes are where most go-live problems start.

Build a test plan from real calls

List the ten to twenty reasons customers call today and write each one as a test case: who calls, from which number, at what time, what they press or say, and where the call should end up. Include the awkward cases:

  • A caller who presses nothing at the IVR.
  • A caller who presses an invalid key twice.
  • A call after hours and on a holiday.
  • A call when every agent is busy, and when no agent is logged in.
  • A caller who hangs up in the queue, to check the callback list.
  • A transfer to another team and back.

User acceptance testing (UAT) checklist

AreaTestPass when
NumbersCall every published number from a mobile on two networksEach number reaches the right IVR or queue
IVRTry every option, the timeout and an invalid keyEach path plays the right prompt and routes correctly
Time conditionsTest business hours, after hours and a holiday overrideCallers hear the right message at each time
QueuesCall with agents busy, then with none logged inQueue music, announcements and timeout destination work
Missed callsHang up while waitingThe call appears in the missed call worklist for callback
Agent consoleLog in, take a call, hold, transfer, conferenceEvery control works on every agent’s machine
CRMAnswer a call from a known customerThe record pops up and click to call works
DispositionsClose a call with each dispositionThe disposition and remark show in reports
RecordingMake a test call and play it backAudio is clear on both sides and access is restricted
SupervisorListen, whisper and barge on a test callEach mode works and the customer hears only what they should
WallboardWatch a test queue fill and emptyFigures match what happened
ReportsRun inbound, agent and abandoned call reportsCounts match the test log

Record each test with a pass or fail and the name of the tester. A fail is fixed and retested, not explained away.

Load and network checks

Ask several agents to take test calls at the same time, including any home or branch agents. Check audio quality, not just connection. In Voxdial Contact Center, the agent console has a call-quality monitor for jitter, packet loss and round-trip time, which makes network problems visible before customers hear them. For remote agents, see VoIP call quality for remote agents.

One week before: the cutover plan

The cutover plan answers one question: how do calls move from the old setup to the new one, and how do they move back if needed?

  1. Choose the cutover time. Pick your quietest hour, usually early morning or a weekend morning, and avoid month-end, sale days and admission peaks.
  2. Decide the order. Move one number or one queue first, check it, then move the rest. A phased cutover is easier to control than a big switch.
  3. Plan the number move. If numbers are ported or trunks are moved, confirm the date and time with your telecom operator in writing and know who to call if it slips.
  4. Write the rollback. Note exactly how to route calls back to the old system, who decides to roll back, and the deadline for that decision.
  5. Name the people. One go-live lead, one technical contact at your vendor, one person at the telecom operator, one supervisor per shift.
  6. Brief agents. Agents should log in, practise for at least one full shift on test calls and know their usernames, break reasons and dispositions before day one.

Go-live day: hypercare

  • Have the vendor’s engineer available on site or on a call for the first shift.
  • Make test calls to every number right after cutover, before customers notice a problem.
  • Keep the wallboard on a big screen and watch queue length, longest wait and abandoned calls.
  • Run a short check-in every two hours with supervisors: what failed, what confused agents, what callers complained about.
  • Keep a simple issue log with time, problem, owner and fix.
  • Call back every missed caller from the worklist the same day.

The first two weeks: stabilise

  • Daily review of missed calls, abandoned calls by queue and IVR, and agent performance. See call centre reports for what to read.
  • Listen to recordings from each queue to catch prompts that confuse callers or routing that sends calls to the wrong team.
  • Check dispositions. If agents choose “Other” too often, the list needs fixing.
  • Tune the IVR. If many callers time out or press zero at one menu, simplify it.
  • Compare reports with reality. Supervisors’ sense of the day should match the numbers. If it does not, check report settings before changing staffing.
  • Close the issue log. Every open item gets an owner and a date.

Common go-live mistakes

  • Testing only from an office extension, never from a real mobile on the public network.
  • Forgetting after-hours and holiday paths until the first evening.
  • Leaving agents to learn the console with live customers on the line.
  • No rollback plan, so a trunk problem means hours of lost calls.
  • Turning on AI backup or new channels on the same day as the phone cutover. Add one change at a time; AI should come in only as a backup once agents and queues are stable.

Planning a contact centre launch or a move from an old system? Talk to BitVoice about testing and cutover support.

FAQs

What is UAT in a call centre project?

User acceptance testing is the stage where the people who will run the call centre test every call path, console function and report against agreed pass criteria before real customers call.

How long should call centre testing take?

Plan at least one to two weeks of UAT after the design is frozen, plus a full practice shift for agents. Larger centres with many queues or integrations need longer.

Should we switch all numbers on the same day?

Not if you can avoid it. Moving one number or queue first, checking it and then moving the rest makes problems smaller and easier to fix.

What should a rollback plan include?

How calls are routed back to the old setup, who decides to roll back, the deadline for that decision, and the contacts at your vendor and telecom operator.